Project Status Report – ERP Upgrade
Reporting period: 12/29/2025 – 01/12/2026
Prepared by: Christopher Peters, Project Manager
Page 1 of 3

1. Overall status
Overall status is yellow: work is progressing, but one milestone has moved. The budget is under control.

Completed this period:
- requirements analysis finished and signed off by key users,
- test environment set up and first acceptance tests run,
- risk register and communication plan updated,
- all open requests from the previous period closed except one.

2. Budget and changes
The steering committee approved the following amounts:
- Accounting software: $7,000
- Staff training: $3,000
- Marketing campaign: $4,000

Change request CR-10: Timothy Larson requested an increase of the amount for the licenses and rollout of the new accounting software to $9,000. The steering committee rejected the request; the approved amount of $7,000 stands.
For comparison, last year the "staff training" item cost $2,000.

3. Schedule
The original deadline for the interim report, 04/15/2026, moves to 05/01/2026 because the numbers from accounting are still missing. The steering committee approved the change; the original date no longer applies.

4. Next steps
- Prepare the interim report for senior management – owner: Danielle Little, due 05/01/2026
- Order the equipment and arrange installation – owner: Timothy Larson, due 03/22/2026

5. Risks
Internal capacity is the main risk. Senior management has been informed and has promised additional staff.

6. Communication
Key users were informed about the changes at the regular user meeting. Current project information is available on the intranet; please send any questions to the project team.

The next status report will follow the steering committee meeting on 01/26/2026.

Verdict

Le moins cher sans erreur : Gemma 4 31B, à 0,11 € pour 1 000 documents.

  • Mistral Large 4 ne fait aucune erreur non plus, mais coûte 60,1× plus cher.

Prompt soumis à chaque modèle

Summarize the document below (meeting minutes, a project status report or an email thread) in at
most 80 words.

Rules:
- Include every final decision: the approved amounts, the deadlines that apply and the people
  responsible for the action items (full names).
- Do not mention rejected proposals or their amounts, and do not mention deadlines that were
  changed (the original dates); state only the deadlines that apply.
- Copy amounts and dates exactly as in the document; do not round them.
- Write in the language of the document, factually and in a formal register, as running text
  without headings.
- Return only JSON in the form {"summary": "…"}.

Notre notation

Correspondance exacte par champ, après normalisation des dates, des montants et des espaces. Les diacritiques manquants comptent comme une erreur. Le coût correspond à la consommation réelle de tokens de cette exécution, convertie au taux indiqué en bas de page.

Gratuit après connexion

Les résultats de tous les modèles pour ce document, champ par champ. Les trois premiers exemples de chaque tâche sont libres.

Juste un e-mail, sans mot de passe.

Connexion par e-mail

Nous utilisons votre e-mail uniquement pour la connexion (et le résumé si vous le cochez). Pas de spam.