Project Status Report – Customer Portal
Reporting period: July 28, 2026 – August 11, 2026
Prepared by: Beverly Moore, Project Manager
Page 1 of 4

1. Overall status
We rate the project yellow overall. The main work is on schedule, but the steering committee had to approve a change to one deadline.

Completed this period:
- requirements analysis finished and signed off by key users,
- test environment set up and first acceptance tests run,
- risk register and communication plan updated,
- all open requests from the previous period closed except one.

2. Budget and changes
The steering committee approved the following amounts:
- Marketing campaign: $30,000
- Office remodel: $4,500

Change request CR-04: Kyle Schwartz requested an increase of the amount for the fall marketing campaign to $48,000. The steering committee rejected the request; the approved amount of $30,000 stands.
For comparison, last year the "office remodel" item cost $3,000.

3. Schedule
The original deadline for the signing of the vendor contract, September 27, 2026, moves to October 25, 2026 because the vendor has not yet sent the revised draft. The steering committee approved the change; the original date no longer applies.

4. Next steps
- Prepare and sign the vendor contract – owner: Kyle Schwartz, due October 25, 2026
- Issue the request for proposals – owner: Nicholas Jackson, due November 30, 2026

5. Risks
The main risk remains vendor availability over the summer. The team is monitoring it and will propose measures if needed.

6. Communication
Key users were informed about the changes at the regular user meeting. Current project information is available on the intranet; please send any questions to the project team.

The next status report will follow the steering committee meeting on August 25, 2026.

Veredicto

El más barato sin errores: Gemma 4 31B, a 0,11 € por cada 1000 documentos.

  • GPT-6 Sol tampoco comete errores, pero es 42× más caro.

Prompt enviado a todos los modelos

Summarize the document below (meeting minutes, a project status report or an email thread) in at
most 80 words.

Rules:
- Include every final decision: the approved amounts, the deadlines that apply and the people
  responsible for the action items (full names).
- Do not mention rejected proposals or their amounts, and do not mention deadlines that were
  changed (the original dates); state only the deadlines that apply.
- Copy amounts and dates exactly as in the document; do not round them.
- Write in the language of the document, factually and in a formal register, as running text
  without headings.
- Return only JSON in the form {"summary": "…"}.

Cómo puntuamos

Coincidencia exacta por campo tras normalizar fechas, importes y espacios. La falta de diacríticos cuenta como error. El coste es el gasto real en tokens de esta ejecución, convertido al tipo de cambio indicado en el pie de página.

Gratis al iniciar sesión

Los resultados de todos los modelos para este documento, campo a campo. Los tres primeros ejemplos de cada tarea son libres.

Solo su correo, sin contraseña.

Acceso por correo electrónico

Usamos su correo solo para el acceso (y para el resumen si lo marca). Sin spam.