ModelVerdict

Jason Davis, Danny Hughes

Englisch (USA)Dokument6 Felder

Dokument en-p0014 · Layout status · 6 Felder · öffentlicher Teil des Datensatzes · Dieselbe Rechnung auf Tschechisch → · Fehler in diesem Beispiel melden

Dokumenttext (das Modell hat genau diesen Text erhalten)

Project Status Report – Warehouse Modernization
Reporting period: 04/21/2025 – 05/05/2025
Prepared by: William Archer, Project Manager
Page 1 of 2

1. Overall status
Overall status is yellow: work is progressing, but one milestone has moved. The budget is under control.

Completed this period:
- requirements analysis finished and signed off by key users,
- test environment set up and first acceptance tests run,
- risk register and communication plan updated,
- all open requests from the previous period closed except one.

2. Budget and changes
The steering committee approved the following amounts:
- Marketing campaign: $57,000
- Staff training: $10,000
- External consultants: $11,500

Change request CR-03: Danny Hughes requested an increase of the amount for the fall marketing campaign to $81,000. The steering committee rejected the request; the approved amount of $57,000 stands.
For comparison, last year the "staff training" item cost $7,000.

3. Schedule
The original deadline for the request for proposals, 06/02/2025, moves to 06/30/2025 because legal is still reviewing the RFP documents. The steering committee approved the change; the original date no longer applies.

4. Next steps
- Issue the request for proposals – owner: Jason Davis, due 06/30/2025
- Organize the training and send out invitations – owner: Danny Hughes, ongoing

5. Risks
The main risk remains vendor availability over the summer. The team is monitoring it and will propose measures if needed.

6. Communication
Key users were informed about the changes at the regular user meeting. Current project information is available on the intranet; please send any questions to the project team.

The next status report will follow the steering committee meeting on 05/19/2025.

Fazit

Am günstigsten ohne Fehler: Gemma 4 31B für 0,11 € pro 1.000 Dokumente.

  • Mistral Large 4 ist ebenfalls fehlerfrei, aber 57,5× teurer.

Prompt für alle Modelle

Summarize the document below (meeting minutes, a project status report or an email thread) in at
most 80 words.

Rules:
- Include every final decision: the approved amounts, the deadlines that apply and the people
  responsible for the action items (full names).
- Do not mention rejected proposals or their amounts, and do not mention deadlines that were
  changed (the original dates); state only the deadlines that apply.
- Copy amounts and dates exactly as in the document; do not round them.
- Write in the language of the document, factually and in a formal register, as running text
  without headings.
- Return only JSON in the form {"summary": "…"}.

So bewerten wir

Exakte Übereinstimmung pro Feld nach Normalisierung von Datumsangaben, Beträgen und Leerzeichen. Fehlende diakritische Zeichen zählen als Fehler. Die Kosten sind der reale Tokenverbrauch dieses Laufs, umgerechnet zum Kurs in der Fußzeile.

Kostenlos nach Anmeldung

Die Ausgaben aller Modelle zu diesem Dokument, Feld für Feld. Die ersten drei Beispiele jeder Aufgabe sind frei.

Nur E-Mail, kein Passwort.

Anmeldung per E-Mail

Wir nutzen Ihre E-Mail nur für die Anmeldung (und die Übersicht, wenn Sie sie ankreuzen). Kein Spam.