Project Status Report – Warehouse Modernization
Reporting period: 04/30/2026 – 05/14/2026
Prepared by: Jesse Chase, Project Manager
Page 1 of 4

1. Overall status
We rate the project yellow overall. The main work is on schedule, but the steering committee had to approve a change to one deadline.

Completed this period:
- requirements analysis finished and signed off by key users,
- test environment set up and first acceptance tests run,
- risk register and communication plan updated,
- all open requests from the previous period closed except one.

2. Budget and changes
The steering committee approved the following amounts:
- External consultants: $29,000
- Equipment purchase: $20,000
- Marketing campaign: $10,500

Change request CR-12: Angela Harmon requested an increase of the amount for outside consultants on the process review to $44,000. The steering committee rejected the request; the approved amount of $29,000 stands.
For comparison, last year the "equipment purchase" item cost $12,000.

3. Schedule
The original deadline for the interim report, 06/08/2026, moves to 07/08/2026 because the numbers from accounting are still missing. The steering committee approved the change; the original date no longer applies.

4. Next steps
- Prepare the interim report for senior management – owner: Angela Harmon, due 07/08/2026
- Prepare and sign the vendor contract – owner: Angela Harmon, due 06/18/2026

5. Risks
Internal capacity is the main risk. Senior management has been informed and has promised additional staff.

6. Communication
Key users were informed about the changes at the regular user meeting. Current project information is available on the intranet; please send any questions to the project team.

The next status report will follow the steering committee meeting on 05/28/2026.

Veredicto

El más barato sin errores: GPT-6 Luna, a 0,09 € por cada 1000 documentos.

  • Mistral Large 4 tampoco comete errores, pero es 52,2× más caro.

Prompt enviado a todos los modelos

Summarize the document below (meeting minutes, a project status report or an email thread) in at
most 80 words.

Rules:
- Include every final decision: the approved amounts, the deadlines that apply and the people
  responsible for the action items (full names).
- Do not mention rejected proposals or their amounts, and do not mention deadlines that were
  changed (the original dates); state only the deadlines that apply.
- Copy amounts and dates exactly as in the document; do not round them.
- Write in the language of the document, factually and in a formal register, as running text
  without headings.
- Return only JSON in the form {"summary": "…"}.

Cómo puntuamos

Coincidencia exacta por campo tras normalizar fechas, importes y espacios. La falta de diacríticos cuenta como error. El coste es el gasto real en tokens de esta ejecución, convertido al tipo de cambio indicado en el pie de página.

Gratis al iniciar sesión

Los resultados de todos los modelos para este documento, campo a campo. Los tres primeros ejemplos de cada tarea son libres.

Solo su correo, sin contraseña.

Acceso por correo electrónico

Usamos su correo solo para el acceso (y para el resumen si lo marca). Sin spam.