Project Status Report – Warehouse Modernization
Reporting period: December 31, 2024 – January 14, 2025
Prepared by: Jacqueline Sheppard, Project Manager
Page 1 of 4

1. Overall status
Overall status is yellow: work is progressing, but one milestone has moved. The budget is under control.

Completed this period:
- requirements analysis finished and signed off by key users,
- test environment set up and first acceptance tests run,
- risk register and communication plan updated,
- all open requests from the previous period closed except one.

2. Budget and changes
The steering committee approved the following amounts:
- Staff training: 76,000 USD
- Marketing campaign: 4,500 USD

Change request CR-03: Steven Scott requested an increase of the amount for staff training to 124,000 USD. The steering committee rejected the request; the approved amount of 76,000 USD stands.
For comparison, last year the "marketing campaign" item cost 3,500 USD.

3. Schedule
The original deadline for the equipment delivery, March 29, 2025, moves to April 13, 2025 because the supplier reports shipping delays. The steering committee approved the change; the original date no longer applies.

4. Next steps
- Order the equipment and arrange installation – owner: Mary Harrington, due April 13, 2025
- Launch the campaign and prepare the web content – owner: Mary Harrington, due May 2, 2025

5. Risks
Internal capacity is the main risk. Senior management has been informed and has promised additional staff.

6. Communication
Key users were informed about the changes at the regular user meeting. Current project information is available on the intranet; please send any questions to the project team.

The next status report will follow the steering committee meeting on January 28, 2025.

Verdict

Cheapest with no errors: Gemma 4 31B at $0.11 per 1,000 documents.

  • Mistral Large 4 is also error-free, but 64.1× more expensive.

Prompt given to every model

Summarize the document below (meeting minutes, a project status report or an email thread) in at
most 80 words.

Rules:
- Include every final decision: the approved amounts, the deadlines that apply and the people
  responsible for the action items (full names).
- Do not mention rejected proposals or their amounts, and do not mention deadlines that were
  changed (the original dates); state only the deadlines that apply.
- Copy amounts and dates exactly as in the document; do not round them.
- Write in the language of the document, factually and in a formal register, as running text
  without headings.
- Return only JSON in the form {"summary": "…"}.

How we score

Exact match per field after normalizing dates, amounts, and whitespace. Missing diacritics count as an error. Cost is the actual token spend of this run, converted at the rate shown in the footer.

Free with login

Every model's output for this document, field by field. The first three examples of each task are open.

Just your email, no password.

Log in with email

We use your email only to log you in (and for the digest if you tick it). No spam.