Project Status Report – ERP Upgrade
Reporting period: 01/12/2026 – 01/26/2026
Prepared by: Robert Turner, Project Manager
Page 1 of 2

1. Overall status
We rate the project yellow overall. The main work is on schedule, but the steering committee had to approve a change to one deadline.

Completed this period:
- requirements analysis finished and signed off by key users,
- test environment set up and first acceptance tests run,
- risk register and communication plan updated,
- all open requests from the previous period closed except one.

2. Budget and changes
The steering committee approved the following amounts:
- Marketing campaign: $12,500
- External consultants: $4,500
- Staff training: $9,000

Change request CR-17: Mary Foster requested an increase of the amount for the fall marketing campaign to $18,500. The steering committee rejected the request; the approved amount of $12,500 stands.
For comparison, last year the "external consultants" item cost $3,000.

3. Schedule
The original deadline for the campaign launch, 03/01/2026, moves to 03/25/2026 because the agency needs more time for the creative work. The steering committee approved the change; the original date no longer applies.

4. Next steps
- Launch the campaign and prepare the web content – owner: Nathan Gonzalez, due 03/25/2026
- Prepare the interim report for senior management – owner: Nathan Gonzalez, due 05/05/2026

5. Risks
The main risk remains vendor availability over the summer. The team is monitoring it and will propose measures if needed.

6. Communication
Key users were informed about the changes at the regular user meeting. Current project information is available on the intranet; please send any questions to the project team.

The next status report will follow the steering committee meeting on 02/09/2026.

Verdict

Cheapest with no errors: Gemma 4 31B at $0.12 per 1,000 documents.

  • Gemini 3.8 Flash is also error-free, but 47.5× more expensive.

Prompt given to every model

Summarize the document below (meeting minutes, a project status report or an email thread) in at
most 80 words.

Rules:
- Include every final decision: the approved amounts, the deadlines that apply and the people
  responsible for the action items (full names).
- Do not mention rejected proposals or their amounts, and do not mention deadlines that were
  changed (the original dates); state only the deadlines that apply.
- Copy amounts and dates exactly as in the document; do not round them.
- Write in the language of the document, factually and in a formal register, as running text
  without headings.
- Return only JSON in the form {"summary": "…"}.

How we score

Exact match per field after normalizing dates, amounts, and whitespace. Missing diacritics count as an error. Cost is the actual token spend of this run, converted at the rate shown in the footer.

Free with login

Every model's output for this document, field by field. The first three examples of each task are open.

Just your email, no password.

Log in with email

We use your email only to log you in (and for the digest if you tick it). No spam.