ModelVerdict

Christine Copeland

Englisch (USA)Dokument6 Felder

Dokument en-p0029 · Layout status · 6 Felder · öffentlicher Teil des Datensatzes · Dieselbe Rechnung auf Tschechisch → · Fehler in diesem Beispiel melden

Dokumenttext (das Modell hat genau diesen Text erhalten)

Project Status Report – ERP Upgrade
Reporting period: August 14, 2025 – August 28, 2025
Prepared by: Christian Jones, Project Manager
Page 1 of 2

1. Overall status
We rate the project yellow overall. The main work is on schedule, but the steering committee had to approve a change to one deadline.

Completed this period:
- requirements analysis finished and signed off by key users,
- test environment set up and first acceptance tests run,
- risk register and communication plan updated,
- all open requests from the previous period closed except one.

2. Budget and changes
The steering committee approved the following amounts:
- Accounting software: 6,500 USD
- Staff training: 70,000 USD
- External consultants: 3,000 USD

Change request CR-08: Christine Copeland requested an increase of the amount for the licenses and rollout of the new accounting software to 10,500 USD. The steering committee rejected the request; the approved amount of 6,500 USD stands.
For comparison, last year the "staff training" item cost 41,000 USD.

3. Schedule
The original deadline for the campaign launch, October 13, 2025, moves to November 12, 2025 because the agency needs more time for the creative work. The steering committee approved the change; the original date no longer applies.

4. Next steps
- Launch the campaign and prepare the web content – owner: Christine Copeland, due November 12, 2025
- Prepare and sign the vendor contract – owner: Christine Copeland, due September 27, 2025

5. Risks
Internal capacity is the main risk. Senior management has been informed and has promised additional staff.

6. Communication
Key users were informed about the changes at the regular user meeting. Current project information is available on the intranet; please send any questions to the project team.

The next status report will follow the steering committee meeting on September 4, 2025.

Fazit

Am günstigsten ohne Fehler: Gemma 4 31B für 0,11 € pro 1.000 Dokumente.

  • Mistral Large 4 ist ebenfalls fehlerfrei, aber 59,2× teurer.

Prompt für alle Modelle

Summarize the document below (meeting minutes, a project status report or an email thread) in at
most 80 words.

Rules:
- Include every final decision: the approved amounts, the deadlines that apply and the people
  responsible for the action items (full names).
- Do not mention rejected proposals or their amounts, and do not mention deadlines that were
  changed (the original dates); state only the deadlines that apply.
- Copy amounts and dates exactly as in the document; do not round them.
- Write in the language of the document, factually and in a formal register, as running text
  without headings.
- Return only JSON in the form {"summary": "…"}.

So bewerten wir

Exakte Übereinstimmung pro Feld nach Normalisierung von Datumsangaben, Beträgen und Leerzeichen. Fehlende diakritische Zeichen zählen als Fehler. Die Kosten sind der reale Tokenverbrauch dieses Laufs, umgerechnet zum Kurs in der Fußzeile.

Kostenlos nach Anmeldung

Die Ausgaben aller Modelle zu diesem Dokument, Feld für Feld. Die ersten drei Beispiele jeder Aufgabe sind frei.

Nur E-Mail, kein Passwort.

Anmeldung per E-Mail

Wir nutzen Ihre E-Mail nur für die Anmeldung (und die Übersicht, wenn Sie sie ankreuzen). Kein Spam.